Home › NZ Building Code › Contracts & Compliance › 12-month Defect Period
NZ Building Code · Contracts & ComplianceThe 12-month defect period under s362Q
Under s362Q of the Building Act, for the first 12 months after completion the onus is on you as the builder to prove work isn’t defective — here’s how that window works and what falls outside it.
Section 362Q of the Building Act sets up a 12-month window after completion where, if a client notifies you of a defect, the onus sits with you as the builder to prove the work isn’t defective. It matters because for that first year the burden of proof runs against you — so knowing exactly what’s covered, and what isn’t, keeps you out of arguments you don’t need to have.
How the 12-month rule works
The rule splits the period after completion into two stages, and the difference between them is who has to prove the work was or wasn’t defective.
- 0–12 months from completion: you must remedy defects when notified, and the onus is on you as the builder to prove the work is not defective.
- 12 months to 10 years: the implied warranties and remedies still apply, but the onus shifts to the client to prove the work is defective.
Once you’re notified of a defect, you’re entitled to a “reasonable amount of time” to fix it (s362M).
When it applies
The rule started on 1 January 2015. It does not apply to contracts signed before that date.
What’s not covered (s362Q exclusions)
The 12-month rule doesn’t make you liable for everything. The following are excluded under s362Q:
- Damage outside human control — natural disaster, earthquake, fire.
- Damage caused by the occupant or owner, or by someone they engaged.
- Damage from a failure to maintain (s362S — the maintenance disclosure obligation).
- Damage from delayed repairs after a defect became apparent.
- Aesthetic preferences above industry norms, unless specified in the contract.
- Reasonable wear and tear.
- Critical lighting imperfections — sunlight at an angle of 15° or less (see the Tolerance Guide).
- Imperfections caused by occupant misuse, such as poor ventilation or water damage.
Plain-English guide, not advice. This page helps you understand and navigate the rules — it is general information, not design, engineering or consent advice, and it does not reproduce the copyrighted tables of NZS 3604 or any Standard. Always check the current Standard or Acceptable Solution and your BCA, and use a suitably qualified LBP, engineer or QS where it matters.
Do it in Toolie
Put this into practice with LBP Record of Work · the building-consent tracker · retentions & CCA claims. Try Toolie free — no signup — or open this topic in the Toolie app.
Common questions
During the first 12 months, who has to prove whether the work is defective?
The onus is on you as the builder. For the 0–12 month window after completion you must remedy defects when notified, and you have to prove the work is not defective. After 12 months (up to 10 years) the onus shifts to the client to prove the work is defective.
When did the s362Q defect period start, and does it cover older contracts?
It started on 1 January 2015 and does not apply to contracts signed before that date.
How long do I have to fix a defect once I’m notified?
Section 362M entitles you to a “reasonable amount of time” to fix a defect once you’ve been notified of it.
What kinds of damage are excluded from the 12-month rule?
Exclusions under s362Q include damage outside human control (natural disaster, earthquake, fire), damage caused by the occupant or owner or someone they engaged, damage from a failure to maintain (s362S), damage from delayed repairs after a defect became apparent, aesthetic preferences above industry norms unless specified in the contract, reasonable wear and tear, critical lighting imperfections (sunlight at 15° or less), and imperfections caused by occupant misuse such as poor ventilation or water damage.
More in Contracts & Compliance
- NZS 3902:2004 Contract
- 9 Implied Warranties
- Building Act 2004
- Schedule 1 Exemptions
- Granny Flat Exemption 2026
- Resource Consent (RMA)
- Licensed Building Practitioners
- LBP Classes & AoPs
- Heritage Buildings
- Council Consent Fees
- Consent Process Overview
All Contracts & Compliance topics → · Full NZ Building Code index
Quote it, comply, get paid — in one app
Toolie turns this knowledge into the job: NZS 3604 take-off, H1 & Healthy Homes, consents, retentions and invoicing — one flat NZD price.
Quote a job free →