Home › NZ Building Code › Build Sequence › Council Inspections Guide
NZ Building Code · Build SequenceCouncil building inspections: pass first time
Council inspections are mandatory hold points where the BCA checks your work at set stages — and knowing exactly what the inspector looks for is how you pass first time.
Council inspections are mandatory hold points: the BCA (Building Consent Authority) checks the work at set stages, and you can’t carry on past some of them until it passes — you can’t pour over un-inspected reo, or line over un-inspected framing. The stages are listed on your consent, you book each one with a day or two’s notice, and the trick to passing first time is knowing exactly what the inspector checks before they turn up.
Why a failed inspection costs real money
A fail means a re-inspection fee (around $350–400) and the trades stand down until you re-book — easily a week lost. Worse, if you’ve covered work the inspector needs to see, such as lining over bracing or backfilling a drain, you may have to open it back up.
- Self-check against the stage list below before you call the booking in.
- Photograph everything before it’s hidden — reo, wrap, insulation, drains.
The inspection stages, in order
These are the common hold points on a consent. Each one has a “when” you can’t skip past, a set of things the inspector checks, and the usual fixes if something’s short.
1. Siting — after excavation, before pouring footings
The inspector checks:
- Building positioned correctly per consent (boundary setbacks).
- Excavation depth and soil bearing (against the geotech).
- Stormwater diverted away from the work area.
To pass: re-stake if you’re off, and verify with the geotech if the soil is softer than expected.
2. Pre-pour foundations — reinforcing in, before the concrete pour
The inspector checks:
- Reinforcing mesh and bars present and correctly tied (B1/AS1 Amendment 11 — 2× D12).
- DPM 250µm polythene over the base, with laps taped.
- Cover to reinforcing at least 30mm.
- Plumbing and electrical conduits in the correct position.
- Formwork square and level.
- Edge thickening and step-downs correct.
To pass: add starter bars where missing, re-tie if loose, and replace torn DPM.
3. Pre-line / pre-close — framing complete, before plasterboard goes up
The inspector checks:
- Bracing per consent (BU/m capacities marked on the drawings).
- Stud and plate sizes per wind zone.
- Fixing centres correct (top plate to rafter strap centres per Table 10.13).
- Lintel sizes matching the drawings and wind zone.
- Internal services (plumbing and electrical) roughed in within the frame, not damaging the structure.
- Wet-area framing H3.2.
- Insulation in the walls visible and at the correct R-value.
- Building wrap installed and lapped correctly.
To pass: add a bracing element if BU is short, upsize a lintel if it’s under-spec’d, and tape any unlapped wrap.
4. Post-line — plasterboard fixed, before stopping
The inspector checks:
- Plasterboard fixing centres (300mm perimeter, 600mm field).
- Fire-rated walls: correct sheets, screw centres and edge distances.
- Wet area: Aqualine in the shower and 1m beyond, with a gap to the floor.
- Penetrations through fire walls sealed.
To pass: add screws where missing and replace damaged sheets.
5. Drainage — drains installed and tested, before backfill
The inspector checks:
- Pipe diameters correct (100mm WC, 50mm basin, 50mm shower).
- Falls correct (1:60 WC, 1:40 sink).
Plain-English guide, not advice. This page helps you understand and navigate the rules — it is general information, not design, engineering or consent advice, and it does not reproduce the copyrighted tables of NZS 3604 or any Standard. Always check the current Standard or Acceptable Solution and your BCA, and use a suitably qualified LBP, engineer or QS where it matters.
Do it in Toolie
Put this into practice with construction management · inspection readiness · consent tracking. Try Toolie free — no signup — or open this topic in the Toolie app.
Common questions
Why can't I just carry on if I miss an inspection?
Some inspections are mandatory hold points — you can't pour over un-inspected reo or line over un-inspected framing until the BCA has checked and passed that stage. The stages are listed on your consent.
What does a failed inspection actually cost me?
A fail means a re-inspection fee of around $350–400, and the trades stand down until you re-book — easily a week lost. If you've already covered work the inspector needs to see, like lining over bracing or backfilling a drain, you may also have to open it back up.
What does the inspector check at pre-pour foundations?
Reinforcing mesh and bars present and correctly tied, DPM 250µm polythene over the base with laps taped, cover to reinforcing of at least 30mm, plumbing and electrical conduits in position, formwork square and level, and edge thickening and step-downs correct.
How do I give myself the best chance of passing first time?
Know exactly what the inspector checks before they arrive and self-check against the stage list. Photograph everything before it's hidden — reo, wrap, insulation and drains — and book each inspection with a day or two's notice as listed on your consent.
More in Build Sequence
Quote it, comply, get paid — in one app
Toolie turns this knowledge into the job: NZS 3604 take-off, H1 & Healthy Homes, consents, retentions and invoicing — one flat NZD price.
Quote a job free →